Major PSC Pipe Projects completed recently for Karnataka Urban Water Supply and Sewerage Disposal Board and Bangalore Water Supply and Sewerage Disposal Board, Karnataka State |
||||
|
Srno |
Type of Work |
Diameter (mm) |
Test Pressure (M) |
Length in Meter |
|
1 |
Supply, laying, jointing, testing and commissioning of PSC pipeline including allied civil works for Malavally Water Supply Scheme |
400 |
12 & 18 kg/cm2 |
11280 |
|
2 |
Supply, laying, jointing, testing and commissioning of PSC pipeline including allied civil works for Mandya Water Supply Scheme |
600/700 |
12 & 18 Kg/cm2 |
21300 |
|
3 |
Supply, laying, jointing, testing and commissioning of PSC pipeline including allied civil works for Koppal Water Supply Scheme |
450 |
12 Kg/cm2 |
21000 |
|
4 |
Supply, laying, jointing, testing and commissioning of PSC pipeline including allied civil works for Magdi Water Supply Scheme |
375 |
---- |
4000 |
|
PSC Pipe Project completed recently for KPC Bidadi Power Corporation Limited, Bangalore |
||||
|
1 |
Laying, jointing, testing and commissioning of PSC pipeline including allied civil works for Water Supply to C C P Plant at Bidadi |
500 to 800 |
4 to 12 Kg/cm2 |
21180 |
|
|
|
||
|
|
|
||
|
|
|||